If a schedule has an end time or limited actions, it will delete itself one week after the last action. This will show up as the schedule not existing, and the underlying internal workflow being “terminated”. After that, the usual namespace retention period will apply and the internal workflow will be deleted after that further time. But you can reuse the schedule id after the first period, you don’t need to wait for the second one.